40.8 MWp Ground Mount Solar Project in Wolfsgarten, Germany

- Capacity
- 40.8 MWp
- System type
- Ground Mount
- Location
- Wolfsgarten, Germany
- Build period
- Oct 2023 - Feb 2024
Project overview
This 40.8 MWp ground mount photovoltaic system was delivered in Wolfsgarten, Germany, with construction during Oct 2023 - Feb 2024. The scope covered engineering, procurement and construction — layout and yield design, structural and electrical engineering, module and inverter supply, mounting, DC and AC installation, grid connection works, testing and commissioning.
As a ground-mount plant, the works included site preparation, pile-driven mounting structures, internal cable routing, inverter and transformer stations, medium-voltage connection, fencing and security infrastructure. Row spacing and tilt were optimised for the local irradiation profile and terrain.
Scope of works
- • Site survey and feasibility assessment
- • Layout, yield modelling and electrical design
- • Module, inverter and mounting procurement
- • Mechanical installation and DC/AC works
- • Grid connection coordination and protection settings
- • Testing, commissioning and handover documentation